KING CHARLES COURT SHELTERED HOUSING UNIT

CHARLES COURT SHELTERED HOUSING UNIT

CLIENT: London Borough of Southwark

CONTRACT: Communal Lighting & Emergency Escape Lighting to Various Sheltered Housing Units (SHU’s)

VALUE : £ 420,000 GBP

BCS Ltd were contracted to carry out renewal of emergency lighting installation to 10 Sheltered Housing units based within the London Borough of Southwark (LBS). One of buildings we carried out an emergency lighting upgrade to was King Charles House. This building was consistently occupied by residents and as part of a  Electrical Installation Condition Report & Emergency Periodic Testing Certification we identified in consultation with LBS and the NICEIC that these building needed drastic works to upgrade after The London Fire Brigade had imposed notices upon these buildings. , which formed part of the works to carry out PPM to communal lighting within the sheltered housing unit FRA works. This was to Highlight age and condition of Installation also to determine if any deterioration of services/risks of fire or electrocution. These tests are carried out incompliance with BS 7671 requirements for electrical installation, and BS5266 emergency lighting BS standard.

QUALITY CONTROL

BCS Ltd is fully accredited to ISO 9001, EXOR, CHAS, and Construction Line NICEIC, Trust Mark, and staffs are constantly monitored on an ongoing basis and their training reviewed to ensure competence.  All of these accreditation required independent auditing, management structures to ensure suitable quality control measures are in place. This required the implementation of applicable key performance indicators to ensure quality control targets have been met. Prior to work commencing, the works site was be subjected to a comprehensive Risk Assessment followed by a detailed method statement identifying all work aspects.. During the initial mobilisation period BCS ltd employees are made aware of the exact requirement and the expectation of all stakeholders.  Supervisors and Project Managers are instructed to carry out random spot checks on all work in progress to quickly identify poor standards and make immediate improvements.

BCS Ltd ensured housekeeping was kept throughout this contact; records were always kept up to date, paperwork was readily available for the client.  Invoicing was carried out in line with the request of the client and information was always up to date and available for the client.

EXAMPLES OF COLLABORATIVE WORKING WITH CLIENT AND RESIDENTS

The initial contract meeting was used as an introduction to all parties so that all key stakeholders could engage effectively.

We ensured a relationship was formed from the offset, utilising our Resident Liaison Officer.  A formal introduction was also made with the Sheltered Housing Unit Manager of King Charles Court. Our Resident Liaison Officer was given the duty of identify and assessing all the residents special needs this allowed BCS Ltd to tailor their working programme to minimise disruption and inconvenience to tenants.  Our RLO identified a multi-lingual resident base and ensured the relevant communication channels were covered; this resulted in notices and signage throughout the block drafted in several languages.

Communication was essential in order for this project to run effectively by involving clients and residents collectively.  We achieved this by arranging frequent site meetings and tenant and residents meetings.  An example of collaboration and working in partnership with the client was demonstrated following a TRA meeting attended by BCS ltd and the Client Representative.  During this meeting the residents requested electricity supplies were not interrupted during the Olympic Events for 2012.  BCS Limited were able to modify the programme of works to prevent disruption for the residents, by installing temporary electrical supplies to the essential supplies with building.

We scheduled weekly progress meetings with the London Borough of Southwark to ensure they were updated on any timescale issues and gave them the opportunity to prevent any issues from escalating and gave working groups a high level platform for the client to air their views.

Throughout this contract BCS Ltd put in procedures to deal with vulnerable residents and safe systems or work implemented to allow for Fire detection system and essential supplies to be operational at all times so to cause minimum disruption

BCS-Ltd also worked in a partnership with LBS as they had previously carried out a pilot scheme for LED Energy Efficient Lighting for Brockley House.  BCS Ltd reviewed the similarities between the two premises and also made a recommendation for the use of LED lights to be fitted within Kings Charles Court.  The review showed that Kings Charles Court could reduce energy usage and costs by up to 55%.

QUALITY CONTROL PROCEDURES

  • Pre Start meetings with LBS
  • Standard of expected terms of delivery and quality
  • KPI were addressed and incorporated with our works procedures
  • Gant chart forming critical path a schedule of works
  • Adequate procurement procedures  for supply chain & materials
  • Ensuring that final handover is documented correctly and detail
  • Tenant Satisfaction and concerns addressed at two weekly meetings.

DETAILS OF DAY TO DAY MANAGEMENT AND SUPERVISION

For the duration of this contract the contract manager visited the site on a daily basis to carry out the following:

Provide the adequate supervision for employees and contractors throughout the duration of this contract.

Oversaw Waste Management on Site and that Waste Transfer Notes were obtained where required.

Ensured materials and chemicals are suitably identified and stored

Ensured materials had been procured in line with the programme of works.

Requested COSHH/E information if this was not provided and ensured advice was followed.

Coordinate Planned Arrangements for any Emergency Situations that occurred.

Reported instances of non-conformance and any near misses identified during the operation of this contract.

Site Attendance Records were carried out on a daily basis to audit safe access and egress to and from site.

The site manager also carried out checks to ensure the programme of works had been adhered too.

RESOURCE STRUCTURE

For this contract the management team had been set up to manage, supervise and co-ordinate staff as follows:

Directors

Endorse implementation of Quality Management Systems through application of the quality policy statement and routine involvement.

Ensure adequate resources are made available.

 Contract Manager

The contract manager ensured the adequate supervision of both employees and contractors.  Their major role was to make sure the project ran to schedule, and met the required standard.  The contract manager was also heavily involved in the Health and Safety Management of the site.

Resident Liaison Officer

The RLO was the communication hub between residents, housing officers and contractor.

Site Supervisor

Monitored the labour workforce, and ensured the programme was met within the deadline set.  A major role of the site supervisor was also to ensure safe working practices at all times.  Inspections of general housekeeping including ensuring the right materials and plant were on-site at the right time for the King Charles Court project and ensured professional conduct of staff on site at all times.

Electricians

The electricians maintained the installation to the client specification. They were fully aware of the requirement and stakeholders before they entered the site.  They were also aware of how to contact the relevant site staff if they had any problems or issues that needed to be addressed.

Health and Safety Officer

Monitored on site activity and ensured compliance with health and safety legislation.  Ran tool box talk’s to contractors before they were allowed on site.  Carried our regular site reviews and inspections from a H&S perspective.

First Aider

Provided immediate first aid when required and reported any accidents, as some electricians are also first aiders.

Administrative / Co-ordinator

Collate all on-site documentation generated throughout the duration of the project.  Ensured communication and continuity channels were maintained to deliver a successful service.

Health & Safety Provisions

  • Obtaining a safe working environment for staff and general public
  •  Tool box were carried out on a weekly basis
  • COSHH Report updated on particular i.e. hazardous substances
  • Asbestos identify and correct PPE was put in place
  • Issuing of site ware fare need and requirements
  • Ensuring that a signing in procedure was adhered to
  • Ensure method statement & Risk assessment are signed off and agreed
  • Notification of designated escape routes are shown before commencement of site
  • Permit of works & Hot Work Permits
  • Identify Risks in shutting down supplies i.e Lifts, Water Pumps. Maintaining Fire alarm systems etc.

BCS Ltd completed these works within time and budget and was awarded further emergency lighting upgrades to various tower blocks within the London Borough Of Southwark . We displayed professionalism at all times in quality of works and in conduct towards residents. We have demonstrated that BCS Ltd carry out these works offering value for money and quality of works. References available upon request.